Month 1
Council approval; shredder purchase; DEWATS excavation; vermi concrete; TLUD welding.
Waste & sanitation masterplan — Culasi, Antique, Philippines. Full briefing for Barangay Capitana and Sangguniang Barangay.
Author: Marián Kapitán · Version: 1.1 · July 2026
Purpose: Briefing pack for the Punong Barangay (Capitan) and Sangguniang Barangay (Kagawad).
Camancijan (~2,000 residents) needs a dual track: community wastewater (DEWATS) and a zero-waste alternative to open burning (pagsunog). This page carries the full masterplan content in English; the original Slovak PDF remains the document for council sessions.
Under the Local Government Code of 1991, the barangay is the smallest LGU with its own budget. Camancijan does not hold large capital, but it has legally guaranteed revenues.
| Source | Description |
|---|---|
| NTA (former IRA) | Main income — share of national taxes by population and land area |
| RPT 25% | Share of real property tax collected on barangay territory |
| Own fees | Barangay Clearance, hall rental, sari-sari fees |
| External grants | Municipality of Culasi, Province of Antique, Congressional Funds |
Funds cannot be invested in stocks or speculative assets. “Investment” means capital spending on local development:
The Capitan does not decide major investments alone. Every significant financial decision is approved by the Sangguniang Barangay (7 Kagawad + SK). The Capitan may operationally use the 5% emergency fund and small operating purchases. Large projects (Mega Dike, municipal sewerage) are funded by DPWH / province / municipality — the Capitan lobbies through a Resolution.
Local “septics” (imburnal / dry wells of hollow blocks without a floor) act as soakaways. Kitchen greywater often discharges onto the lot. Wells (poso) often are not at the legally recommended distance of ≥ 15 m → drinking-water contamination (E. coli).
A complete network + treatment plant costs millions of PHP. Camancijan’s annual budget is in the hundreds of thousands to low millions of PHP; the Development Fund is only a fraction. Responsibility split:
| Parameter | Value |
|---|---|
| Street length | ~150 m (Purok 3) |
| Homes / families / people | 12 / 15 / ~75 |
| Daily flow | ~5 m³/day (100 L/person) |
| Septic volume | min. 15–18.75 m³ (3-day HRT) |
| Design | 3-chamber reinforced concrete (50% / 25% / 25%) |
| Estimate (network + septic + sludge drying) | ₱43,500 – ₱196,400 by scope |
~₱189,500–196,400 covers a full network + septic for ~10–12 homes including skilled labour. The lower ₱43,500 line in the masterplan is the material core / pilot without full labour — always pin the exact street before approval.
Every 12–18 months: desludging → Sludge Drying Bed (UV + drying) → co-composting with biochar at the vermi station → safe fertilizer for non-food crops / trees.
RA 9003 and RA 8749 ban open burning, yet it persists in the field. Burning palay, palm fronds, corn cobs and bunot produces:
Response: three zero-waste pillars plus BHW education (children’s and elders’ health outweighs paper laws alone).
| Input | Coconut fronds, bunot, branches, corn cobs |
|---|---|
| Technology | Mobile shredder 7.5 HP + 2× TLUD drum reactors |
| Output | Biochar to soil (water + nutrients) |
| Cost | Shredder ₱29,180 + TLUD ₱5,600 = ₱34,780 |
| Input | Kitchen waste, soft leaves, (after drying) septic sludge |
|---|---|
| Technology | 3 concrete bins at the MRF + African Nightcrawler |
| Output | Vermicast (organic fertilizer) |
| Cost | ₱15,950 |
| Input | Pig/poultry manure + kitchen waste |
|---|---|
| Technology | PE tube 10 m, manometer, low-pressure stove |
| Output | Cooking gas + digestate; −90% odour |
| Cost | ₱9,775 (1 pilot household) |
| Item | PHP |
|---|---|
| Mobile shredder | 29,180 |
| Biochar TLUD (2 units) | 5,600 |
| Vermicompost station | 15,950 |
| Pilot biogas | 9,775 |
| DEWATS + sludge drying (pilot) | 43,500 |
| Total (base masterplan) | 104,005 |
| Option: full street septic for 12 homes | + ~150,000–190,000 |
Financing mix: 20% Development Fund + LGU Culasi / province + Bayanihan + a symbolic maintenance fee (e.g. ₱30/month for desludging).
Council approval; shredder purchase; DEWATS excavation; vermi concrete; TLUD welding.
MRF training; biogas pilot; household connections; sludge drying bed.
Regular bio-waste collection; first biochar/vermicast batch; DEWATS effluent check; present to Culasi.
Approve at the next Barangay Council session:
Join forces for a cleaner, healthier, and more modern Camancijan.